One of the things we had to do for the house prior to delivery was organise someone to level the land. So I had a friend who knew someone that could do the job so we met him on the land one weekend and we pegged out the area. We discussed the options and it was decided hat a hard cut was what is required.
The building company had also specified that where we do the cut that we create a slope so the trucks can roll out.
As it turned out the cut dug in approx 1 metre
- more than I expected. Also the width was a bit narrow and we had to get permission from the council to place the house 7.6 metres from the boundary rather than the specified 8 metres